Window Project






Demand Letters and/or Complaints

 


Tentative Window Project Schedule – as of 4/19/2019

 

Tower C – Line 07 – Tentative Schedule – Updated

Task Name Duration Start Finish
C-1207 4 days Thu 4/18/19 Tue 4/23/19
C-1107 4 days Mon 4/22/19 Thu 4/25/19
C-1007 4 days Tue 4/23/19 Fri 4/26/19
C-907 4 days Wed 4/24/19 Mon 4/29/19
C-807 4 days Thu 4/25/19 Tue 4/30/19
C-707 4 days Fri 4/26/19 Wed 5/1/19
C-607 4 days Mon 4/29/19 Thu 5/2/19
C-507 4 days Tue 4/30/19 Fri 5/3/19
C-407 4 days Wed 5/1/19 Mon 5/6/19
C-307 4 days Thu 5/2/19 Tue 5/7/19
C-207 4 days Fri 5/3/19 Wed 5/8/19

 

Tower C – Line 01 – Tentative Schedule

Task Name Duration Start Finish
C-1201 4 days Tue 5/7/19 Fri 5/10/19
C-1101 4 days Wed 5/8/19 Mon 5/13/19
C-1001 4 days Thu 5/9/19 Tue 5/14/19
C-901 4 days Fri 5/10/19 Wed 5/15/19
C-801 4 days Mon 5/13/19 Thu 5/16/19
C-701 4 days Tue 5/14/19 Fri 5/17/19
C-601 4 days Thu 5/16/19 Tue 5/21/19
C-501 4 days Fri 5/17/19 Wed 5/22/19
C-401 4 days Mon 5/20/19 Thu 5/23/19
C-301 4 days Tue 5/21/19 Fri 5/24/19
C-201 4 days Wed 5/22/19 Mon 5/27/19

 

Tower C – Line 02 – Tentative Schedule

Task Name Duration Start Finish
C-1202 4 days Fri 5/24/19 Wed 5/29/19
C-1102 4 days Mon 5/27/19 Thu 5/30/19
C-1002 4 days Tue 5/28/19 Fri 5/31/19
C-902 4 days Wed 5/29/19 Mon 6/3/19
C-802 4 days Thu 5/30/19 Tue 6/4/19
C-702 4 days Fri 5/31/19 Wed 6/5/19
C-602 4 days Mon 6/3/19 Thu 6/6/19
C-502 4 days Tue 6/4/19 Fri 6/7/19
C-402 4 days Wed 6/5/19 Mon 6/10/19
C-302 4 days Thu 6/6/19 Tue 6/11/19
C-202 4 days Fri 6/7/19 Wed 6/12/19

 

Tower F – Line 07 – Tentative Schedule 

Task Name Duration Start Finish
Rain Day 4-19-2019 1 day Fri 4/19/19 Fri 4/19/19
F-507 4 days Mon 4/22/19 Thu 4/25/19
F-407 4 days Tue 4/23/19 Fri 4/26/19
F-307 4 days Wed 4/24/19 Mon 4/29/19
F-207 4 days Thu 4/25/19 Tue 4/30/19

 

Tower F – Line 01 – Tentative Schedule

Task Name Duration Start Finish
F-1201 4 days Mon 4/29/19 Thu 5/2/19
F-1101 4 days Tue 4/30/19 Fri 5/3/19
F-1001 4 days Wed 5/1/19 Mon 5/6/19
F-901 4 days Thu 5/2/19 Tue 5/7/19
F-801 4 days Fri 5/3/19 Wed 5/8/19
F-701 4 days Mon 5/6/19 Thu 5/9/19
F-501 4 days Tue 5/7/19 Fri 5/10/19
F-601 4 days Wed 5/8/19 Mon 5/13/19
F-401 4 days Thu 5/9/19 Tue 5/14/19
F-301 4 days Fri 5/10/19 Wed 5/15/19
F-201 4 days Mon 5/13/19 Thu 5/16/19


Tower F – Line 02 – Tentative Schedule

Task Name Duration Start Finish
F-1202 4 days Wed 5/15/19 Mon 5/20/19
F-1102 4 days Thu 5/16/19 Tue 5/21/19
F-1002 4 days Fri 5/17/19 Wed 5/22/19
F-902 4 days Mon 5/20/19 Thu 5/23/19
F-802 4 days Tue 5/21/19 Fri 5/24/19
F-202 4 days Wed 5/22/19 Mon 5/27/19
F-702 4 days Thu 5/23/19 Tue 5/28/19
F-602 4 days Fri 5/24/19 Wed 5/29/19
F-502 4 days Mon 5/27/19 Thu 5/30/19
F-402 4 days Tue 5/28/19 Fri 5/31/19
F-302 4 days Wed 5/29/19 Mon 6/3/19


Progress Pictures


 

       

Tower A Lines 01 & 02

Tower A Lines 03 & 04

 

 

Resident Communications
  1. Early Warning– 30 days before commencement of work in a given unit
  2. General Notice including install date 1-3 weeks before commencement of work
  3. Before, during and after install 1-3 weeks before commencement of work
  4. Tennis Court Notification
Resident Feedback Letters.

Windows Replacement Project  

1.  Contract:

Change Orders

2. Permits:

3. NOC & Bond

 

Engineer Consultant 

1. Contract

 

Special Assessment – Window Project

1. Special Assessment & Payment Options

2. Special Assessment Cost Comparison (2014 vs. 2017)