Window Project






Demand Letters and/or Complaints

 


Tentative Window Project Schedule – as of  8/28/2019
ATTENTION – Scheduled installations have been delayed, in order to prepare for hurricane Dorian. Window installations are scheduled to resume on 9/9/2019 weather permitting.
Tower A – Line 05 Schedule  
Task Name Duration Start Finish
A-1105 4 days Mon 9/9/19 Thu 9/12/19
A-1005 4 days Tue 9/10/19 Fri 9/13/19
A-905 4 days Wed 9/11/19 Mon 9/16/19
A-805 4 days Thu 9/12/19 Tue 9/17/19
A-705 4 days Fri 9/13/19 Wed 9/18/19
A-605 4 days Mon 9/16/19 Thu 9/19/19
A-505 4 days Tue 9/17/19 Fri 9/20/19
A-405 4 days Wed 9/18/19 Mon 9/23/19
A-305 4 days Thu 9/19/19 Tue 9/24/19
A-205 4 days Fri 9/20/19 Wed 9/25/19
A-105 4 days Mon 9/23/19 Thu 9/26/19

Tower A – Line 06 Schedule 

Task Name Duration Start Finish
A-1106 4 days Mon 9/9/19 Thu 9/12/19
A-1006 4 days Tue 9/10/19 Fri 9/13/19
A-906 4 days Wed 9/11/19 Mon 9/16/19
A-806 4 days Thu 9/12/19 Tue 9/17/19
A-706 4 days Fri 9/13/19 Wed 9/18/19
A-606 4 days Mon 9/16/19 Thu 9/19/19
A-506 4 days Tue 9/17/19 Fri 9/20/19
A-406 4 days Wed 9/18/19 Mon 9/23/19
A-306 4 days Thu 9/19/19 Tue 9/24/19
A-206 4 days Fri 9/20/19 Wed 9/25/19
A-106 4 days Mon 9/23/19 Thu 9/26/19

Tower A – Line 07 Schedule 

Task Name Duration Start Finish
A-1207 4 days Thu 9/26/19 Tue 10/1/19
A-1107 4 days Fri 9/27/19 Wed 10/2/19
A-1007 4 days Mon 9/30/19 Thu 10/3/19
A-907 4 days Tue 10/1/19 Fri 10/4/19
A-807 4 days Wed 10/2/19 Mon 10/7/19
A-707 4 days Thu 10/3/19 Tue 10/8/19
A-607 4 days Fri 10/4/19 Wed 10/9/19
A-507 4 days Mon 10/7/19 Thu 10/10/19
A-407 4 days Tue 10/8/19 Fri 10/11/19
A-307 4 days Wed 10/9/19 Mon 10/14/19
A-207 4 days Thu 10/10/19 Tue 10/15/19
A-107 4 days Fri 10/11/19 Wed 10/16/19

Tower A – Line 08 Schedule 

Task Name Duration Start Finish
A-1208 4 days Wed 10/16/19 Mon 10/21/19
A-1108 4 days Thu 10/17/19 Tue 10/22/19
A-1008 4 days Fri 10/18/19 Wed 10/23/19
A-908 4 days Mon 10/21/19 Thu 10/24/19
A-808 4 days Tue 10/22/19 Fri 10/25/19
A-708 4 days Wed 10/23/19 Mon 10/28/19
A-608 4 days Thu 10/24/19 Tue 10/29/19
A-508 4 days Fri 10/25/19 Wed 10/30/19
A-408 4 days Mon 10/28/19 Thu 10/31/19
A-308 4 days Tue 10/29/19 Fri 11/1/19
A-208 4 days Wed 10/30/19 Mon 11/4/19
A-108 4 days Thu 10/31/19 Tue 11/5/19

 


Progress Pictures (click on pictures to enlarge)

 

 

 

 

 

 

       

Tower A Lines 01 & 02

Tower A Lines 03 & 04

 

 

Resident Communications
  1. Early Warning– 30 days before commencement of work in a given unit
  2. General Notice including install date 1-3 weeks before commencement of work
  3. Before, during and after install 1-3 weeks before commencement of work
  4. Tennis Court Notification
Resident Feedback Letters.

Windows Replacement Project  

1.  Contract:

Change Orders

2. Permits:

3. NOC & Bond

 

Engineer Consultant 

1. Contract

 

Special Assessment – Window Project

1. Special Assessment & Payment Options

2. Special Assessment Cost Comparison (2014 vs. 2017)