Window Project






Demand Letters and/or Complaints

 


Tentative Window Project Schedule – as of 2/21/2019


Tower B – Line 03 – Tentative schedule

Task Name Duration Start Finish
B-1203 4 days Mon 2/25/19 Thu 2/28/19
B-1103 4 days Tue 2/26/19 Fri 3/1/19
B-1003 4 days Wed 2/27/19 Mon 3/4/19
B-903 4 days Thu 2/28/19 Tue 3/5/19
B-803 4 days Fri 3/1/19 Wed 3/6/19
B-703 4 days Mon 3/4/19 Thu 3/7/19
B-603 4 days Tue 3/5/19 Fri 3/8/19
B-503 4 days Wed 3/6/19 Mon 3/11/19
B-403 4 days Thu 3/7/19 Tue 3/12/19
B-303 4 days Fri 3/8/19 Wed 3/13/19
B-203 4 days Mon 3/11/19 Thu 3/14/19
B-103 4 days Tue 3/12/19 Fri 3/15/19

 

Tower B – Line 04 – Tentative schedule

Task Name Duration Start Finish
B-1204 4 days Mon 2/25/19 Thu 2/28/19
B-1104 4 days Tue 2/26/19 Fri 3/1/19
B-1004 4 days Wed 2/27/19 Mon 3/4/19
B-904 4 days Thu 2/28/19 Tue 3/5/19
B-804 4 days Fri 3/1/19 Wed 3/6/19
B-704 4 days Mon 3/4/19 Thu 3/7/19
B-604 4 days Tue 3/5/19 Fri 3/8/19
B-504 4 days Wed 3/6/19 Mon 3/11/19
B-404 4 days Thu 3/7/19 Tue 3/12/19
B-304 4 days Fri 3/8/19 Wed 3/13/19
B-204 4 days Mon 3/11/19 Thu 3/14/19
B-104 4 days Tue 3/12/19 Fri 3/15/19

 


Tower E – Line 02 – Tentative schedule

Task Name Duration Start Finish
E-1202 4 days Fri 2/8/19 Wed 2/13/19
E-1102 4 days Mon 2/11/19 Thu 2/14/19
E-1002 4 days Tue 2/12/19 Fri 2/15/19
E-902 4 days Wed 2/13/19 Mon 2/18/19
E-802 4 days Thu 2/14/19 Tue 2/19/19
E-702 4 days Fri 2/15/19 Wed 2/20/19
E-602 4 days Mon 2/18/19 Thu 2/21/19
E-502 4 days Tue 2/19/19 Fri 2/22/19
E-402 4 days Wed 2/20/19 Mon 2/25/19
E-302 4 days Thu 2/21/19 Tue 2/26/19
E-202 4 days Fri 2/22/19 Wed 2/27/19
E-102 4 days Mon 2/25/19 Thu 2/28/19

 

Tower E – Line 03 – Tentative schedule

Task Name Duration Start Finish
E-1203 4 days Fri 3/1/19 Wed 3/6/19
E-1103 4 days Mon 3/4/19 Thu 3/7/19
E-1003 4 days Tue 3/5/19 Fri 3/8/19
E-903 4 days Wed 3/6/19 Mon 3/11/19
E-803 4 days Thu 3/7/19 Tue 3/12/19
E-703 4 days Fri 3/8/19 Wed 3/13/19
E-603 4 days Mon 3/11/19 Thu 3/14/19
E-503 4 days Tue 3/12/19 Fri 3/15/19
E-403 4 days Wed 3/13/19 Mon 3/18/19
E-303 4 days Thu 3/14/19 Tue 3/19/19
E-203 4 days Fri 3/15/19 Wed 3/20/19
E-103 4 days Mon 3/18/19 Thu 3/21/19

 

Tower E – Line 04 – Tentative schedule

Task Name Duration Start Finish
E-1204 4 days Fri 3/1/19 Wed 3/6/19
E-1104 4 days Mon 3/4/19 Thu 3/7/19
E-1004 4 days Tue 3/5/19 Fri 3/8/19
E-904 4 days Wed 3/6/19 Mon 3/11/19
E-804 4 days Thu 3/7/19 Tue 3/12/19
E-704 4 days Fri 3/8/19 Wed 3/13/19
E-604 4 days Mon 3/11/19 Thu 3/14/19
E-504 4 days Tue 3/12/19 Fri 3/15/19
E-404 4 days Wed 3/13/19 Mon 3/18/19
E-304 4 days Thu 3/14/19 Tue 3/19/19
E-204 4 days Fri 3/15/19 Wed 3/20/19
E-104 4 days Mon 3/18/19 Thu 3/21/19

 

Tower F – Line 04 – Tentative schedule

Task Name Duration Start Finish
F-1204 4 days Fri 3/1/19 Wed 3/6/19
F-1104 4 days Mon 3/4/19 Thu 3/7/19
F-1004 4 days Tue 3/5/19 Fri 3/8/19
F-904 4 days Wed 3/6/19 Mon 3/11/19
F-804 4 days Thu 3/7/19 Tue 3/12/19
F-704 4 days Fri 3/8/19 Wed 3/13/19
F-604 4 days Mon 3/11/19 Thu 3/14/19
F-504 4 days Tue 3/12/19 Fri 3/15/19
F-404 4 days Wed 3/13/19 Mon 3/18/19
F-304 4 days Thu 3/14/19 Tue 3/19/19
F-204 4 days Fri 3/15/19 Wed 3/20/19

 

Tower F – Line 05 – Tentative schedule

Task Name Duration Start Finish
F-1205 4 days Fri 3/1/19 Wed 3/6/19
F-1105 4 days Mon 3/4/19 Thu 3/7/19
F-1005 4 days Tue 3/5/19 Fri 3/8/19
F-905 4 days Wed 3/6/19 Mon 3/11/19
F-805 4 days Thu 3/7/19 Tue 3/12/19
F-705 4 days Fri 3/8/19 Wed 3/13/19
F-605 4 days Mon 3/11/19 Thu 3/14/19
F-505 4 days Tue 3/12/19 Fri 3/15/19
F-405 4 days Wed 3/13/19 Mon 3/18/19
F-305 4 days Thu 3/14/19 Tue 3/19/19
F-205 4 days Fri 3/15/19 Wed 3/20/19

 


Progress Pictures

 

       

Tower A Lines 01 & 02

Tower A Lines 03 & 04

 

 

Resident Communications
  1. Early Warning– 30 days before commencement of work in a given unit
  2. General Notice including install date 1-3 weeks before commencement of work
  3. Before, during and after install 1-3 weeks before commencement of work
  4. Tennis Court Notification
Resident Feedback Letters.

Windows Replacement Project  

1.  Contract:

2. Permits:

3. NOC & Bond

 

Engineer Consultant 

1. Contract

 

Special Assessment – Window Project

1. Special Assessment & Payment Options

2. Special Assessment Cost Comparison (2014 vs. 2017)