Window Project






Demand Letters and/or Complaints

 


Tentative Window Project Schedule – as of  10/25/2019

Tower A – Line 08 Schedule

 

Task Name Duration Start Finish
A-1208 4 days Thu 10/31/19 Tue 11/5/19
A-1108 4 days Fri 11/1/19 Wed 11/6/19
A-1008 4 days Mon 11/4/19 Thu 11/7/19
A-908 4 days Tue 11/5/19 Fri 11/8/19
A-808 4 days Wed 11/6/19 Mon 11/11/19
A-708 4 days Thu 11/7/19 Tue 11/12/19
A-608 4 days Fri 11/8/19 Wed 11/13/19
A-508 4 days Mon 11/11/19 Thu 11/14/19
A-408 4 days Tue 11/12/19 Fri 11/15/19
A-308 4 days Wed 11/13/19 Mon 11/18/19
A-208 4 days Thu 11/14/19 Tue 11/19/19
A-108 4 days Fri 11/15/19 Wed 11/20/19

 

 


Progress Pictures (click on pictures to enlarge)

 

 

 

 

 

 

       

Tower A Lines 01 & 02

Tower A Lines 03 & 04

 

 

Resident Communications
  1. Early Warning– 30 days before commencement of work in a given unit
  2. General Notice including install date 1-3 weeks before commencement of work
  3. Before, during and after install 1-3 weeks before commencement of work
  4. Tennis Court Notification
Resident Feedback Letters.

Windows Replacement Project  

1.  Contract:

Change Orders

2. Permits:

3. NOC & Bond

 

Engineer Consultant 

1. Contract

 

Special Assessment – Window Project

1. Special Assessment & Payment Options

2. Special Assessment Cost Comparison (2014 vs. 2017)